To bid an insulation job, take off each area from the manufacturer’s data, write a scope that says what the price includes and what it excludes, and read the contract’s indemnity, insurance, waiver and retainage terms before you sign. The terms decide what your insurance is asked to carry.

Take off each area from the manufacturer’s data

Build the takeoff as a list of areas, each with its own measurements, product and R-value. That is also how the federal paperwork for a home job reads. The Federal Trade Commission’s R-value rule tells installers “If you put insulation in more than one part of the house, put the data for each part on the receipt.” It allows a combined receipt “as long as you do not add up the coverage areas or R-values for different parts of the house.”

For loose-fill, the rule says “the receipt must show the coverage area, initial installed thickness, minimum settled thickness, R-value, and the number of bags used.” A takeoff that lists those items for each area can serve as the worksheet for that receipt.

The quantities come from the product’s own data. The rule tells installers “Do not multiply the R-value for one inch by the number of inches you installed.” A blown-in bid reads its bag count from the manufacturer’s label chart and checks the machine settings the chart was built on. Turning quantities into a price is set out in our spray foam pricing guide, and the tools that automate a takeoff are covered in insulation estimating software.

On a home job, a federal duty comes ahead of the sale. The R-value rule says “Before customers agree to buy insulation from you, you must show them the fact sheet(s) for the type(s) of insulation they want.”

What the written scope should name

The scope says what the price includes: the areas, the products, the prep, and what the customer does before and after the crew arrives. For the foam in EPA’s “Guide to Professionally Installing High-Pressure, Two-Component Spray Polyurethane Foam Insulation”, EPA’s working-draft contractor-client checklist gives you an outline, though EPA says it “was prepared as a voluntary aid to protect against potential risks from SPF; it is not a regulatory compliance tool.”

The checklist opens with a “Brief description of work, locations where SPF will be installed, and SPF insulation products to be used.” and asks the contractor to “Include manufacturer, product names, system numbers, seasonal blends, and lot numbers”. It lists “Environmental conditions needed for foam installation, such as air and surface temperature, relative humidity, and surface moisture.” Put those conditions in the scope, with who adjusts them and what happens to the schedule when a day does not meet them.

Occupancy belongs there as well. The checklist says “Clients should expect to vacate the work zone prior to application and not return until a period of time after application.” The spray foam insurance page describes the policies for that work.

Exclusions for what you find in the attic

Exclusions name the conditions the price does not cover, and a bidder can write into them the attic conditions that ENERGY STAR’s guidance for homeowners flags. Its attic air-sealing page says “Some attics have vermiculite insulation, which may contain asbestos, a health hazard.” and “Don’t disturb vermiculite insulation unless you’ve had it tested by an approved lab to be sure it doesn’t contain asbestos.” A bid that finds suspect vermiculite can exclude any work that disturbs it until a test result is in hand.

ENERGY STAR’s do-it-yourself guide for homeowners lists conditions under the heading “You May Need a Contractor to Correct These Problems”, among them “Wet or damp insulation indicating a leaky roof”, kitchen, bathroom and clothes dryer vents that exhaust moist air into the attic instead of outdoors, knob and tube wiring, and, in the guide’s words, “many unsealed and uninsulated recessed “can” lights”. The guide recommends a homeowner consider hiring a contractor to correct such conditions before proceeding, and a bidder can write any of them into the exclusions. For the crew doing blown-in work, the fiberglass and cellulose service page lays out the matching policies.

Indemnity and hold harmless clauses

Read the indemnity clause for whose negligence it reaches. Minnesota’s statute defines an indemnification agreement as “an agreement by the promisor to indemnify, defend, or hold harmless the promisee against liability or claims of liability for damages arising out of bodily injury to persons or out of physical damage to tangible or real property.” Its statute says such an agreement in a building and construction contract “is unenforceable except to the extent that: (1) the underlying injury or damage is attributable to the negligent or otherwise wrongful act or omission, including breach of a specific contractual duty, of the promisor or the promisor’s independent contractors, agents, employees, or delegatees”, with a further exception where “an owner, a responsible party, or a governmental entity agrees to indemnify a contractor directly or through another contractor with respect to strict liability under environmental laws.” Our Minnesota page covers insurance for crews working there.

Ohio’s rule is written differently. Ohio’s Revised Code says that a promise in a contract for the construction, alteration, repair or maintenance of a building, structure, highway, road, appurtenance or appliance, under which the promisee has hired the promisor to perform work, “purporting to indemnify the promisee, its independent contractors, agents, employees, or indemnitees against liability for damages arising out of bodily injury to persons or damage to property initiated or proximately caused by or resulting from the negligence of the promisee, its independent contractors, agents, employees, or indemnitees is against public policy and is void.” The same section does not prohibit a person from buying insurance from an insurer authorized to do business in Ohio for his own protection, or from buying a construction bond. Our Ohio page covers insurance for crews in that state. This post quotes those laws only for the states they govern.

Your liability policy has its own wording on contracts. The commercial general liability form, as Sonoma County’s published sample copy words it, excludes injury or damage “for which the insured is obligated to pay damages by reason of the assumption of liability in a contract or agreement.” That exclusion carves out liability “That the insured would have in the absence of the contract or agreement”, and liability assumed in what the form calls an insured contract, where the injury or damage occurs after the contract is signed. That definition takes in the part of a contract pertaining to your business under which you assume another party’s tort liability for a third person’s bodily injury, or for damage to that person’s property, with listed exceptions, such as a contract that indemnifies a railroad or an architect, engineer or surveyor for specified injury or damage. The form says “Tort liability means a liability that would be imposed by law in the absence of any contract or agreement.” Your own policy’s version decides, and our general liability page reads other parts of that form.

Real-World Scenario: A general contractor invites an insulation owner to bid the attics on a row of townhomes. Her takeoff lists each attic as its own area, with the bag count read from the manufacturer’s chart. The subcontract asks her to indemnify the builder, name it as an additional insured, waive subrogation and accept retainage until the project closes. Before she prices the job, she sends the subcontract to her agent with her quote request, writes an exclusion for an attic that may hold vermiculite insulation, to stand until a lab test is in hand, and asks the builder when retained payments are released.

Additional insured and primary wording

A request to name the general contractor or owner as an additional insured is answered on the policy, not on the certificate. The sample certificate the City of Sierra Madre publishes with its construction insurance samples says “IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed.” Oregon’s Division of Financial Regulation says “The policy contract must either have a blanket additional insured endorsement or the insurer must add the person.” An owner can be exact about the name: on its sample endorsements, New York’s Dormitory Authority (DASNY) writes “Any language like “as per written contract” is not acceptable - DASNY, etc. must be named”. That note is DASNY’s rule for its own work.

The added party’s coverage has edges. The sample ongoing-operations additional insured endorsement says that coverage “only applies to the extent permitted by law”, and it stops applying to injury or damage that occurs after all work on the project that the additional insured, or anyone for it, is to perform at the covered location is completed, other than service, maintenance or repairs, or after the part of your work that caused it has been put into its intended use by someone other than another contractor or subcontractor on the same project.

Primary and noncontributory wording is a separate request. DASNY’s sample endorsement applies it only where “(1) The additional insured is a Named Insured under such other insurance and (2) You have agreed in writing in a contract or agreement that this insurance would be primary and would not seek contribution from any other insurance available to the additional insured.”

Waivers of subrogation on liability and comp

A waiver request asks your insurance company to give up a right it would otherwise hold. The sample liability waiver endorsement gives up the insurance company’s recovery against the party in its schedule “because of payments we make for injury or damage arising out of your ongoing operations”, or out of finished work for that party that falls within the endorsement’s products-completed operations hazard. The endorsement also says “This waiver applies only to the person or organization shown in the Schedule above.”

The sample workers’ compensation waiver says “We will not enforce our right against the person or organization named in the Schedule.” and adds “(This agreement applies only to the extent that you perform work under a written contract that requires you to obtain this agreement from us.)” The same sample certificate says “If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement.” If a subcontract asks for waivers on the liability and comp policies, list them in your quote request, and see our workers’ compensation page for how that policy answers for your crew.

Retainage and the payment terms

Read the payment section for when progress payments come, what is held back, and when the held amount is released. Minnesota’s statute on building and construction contracts says “A progress payment shall not be considered acceptance or approval of any work or waiver of any defects therein.” It says “Retainage on a building and construction contract may not exceed five percent.” On release, it says “The owner or the owner’s agent must release all retainage no later than 60 days after substantial completion subject to the terms of this subdivision.” Those lines are Minnesota’s, and the subdivision does not apply to a public agency as the statute defines it or to contracts for professional services as it defines them; for a job in another state, read that state’s own statute.

Federal jobs and the FAR clauses

On a federal construction job, read the clauses the contract carries from the Federal Acquisition Regulation. The FAR’s guidance on progress payments under construction contracts says “Retainage should not be used as a substitute for good contract management, and the contracting officer should not withhold funds without cause.”

The FAR’s clause on insurance for work on a Government installation says “Before commencing work under this contract, the Contractor shall notify the Contracting Officer in writing that the required insurance has been obtained.” It tells the prime to put its substance in subcontracts that require work on a Government installation and to require subcontractors “to provide and maintain the insurance required in the Schedule or elsewhere in the contract”. Bonds are a separate subject; the bond guide takes them up.

Send the contract with your quote request

Before you sign, put the contract’s insurance asks beside your policies. Oregon’s Division of Financial Regulation says “Certificates of insurance are not the same as an insurance policy.”

Gather the indemnity clause, the insurance section with its additional insured, primary wording and waiver requests, and the limits the contract names. Where those amounts sit above your liability limits, our umbrella liability page explains how an umbrella policy works with the policies beneath it, and our insulation business insurance overview starts the wider picture. This guide describes these terms as their sources write them; what a clause means for your business is a question for your attorney. Then request a quote with the contract attached, and an agent can match your endorsements to the contract’s asks.

The order of an insulation bid, from the takeoff to the contract terms that reach the policy

A flow in order. Take off each area of the building on its own. Read the manufacturer’s chart or fact sheet for the product. Write the scope in plain terms, then name the conditions you will not touch. Read the indemnity clause, then the insurance section with its additional insured, primary wording and waiver requests, then the payment and retainage terms. Finally, send the contract with your quote request so the policy can be matched to what it asks. No figures are shown.

Frequently asked questions

How to bid insulation jobs: where does the bid start?

Start with the takeoff, area by area, using the manufacturer’s data for each product. The FTC’s R-value rule tells installers “To figure out the R-value of the insulation, use the data that the manufacturer gives you.” Where a home job covers different parts of the house, it says each part’s data goes on the receipt, without adding up coverage areas or R-values. Then write the scope and its exclusions, and read the contract’s indemnity, insurance, waiver and retainage terms before you sign.

How to bid a spray foam insulation job: what goes in the scope?

Use EPA’s working-draft checklist for contractors and clients when the job is the foam in its “Guide to Professionally Installing High-Pressure, Two-Component Spray Polyurethane Foam Insulation”, though EPA says “it is not a regulatory compliance tool.” It starts with a “Brief description of work, locations where SPF will be installed, and SPF insulation products to be used.”, lists the air and surface temperature, humidity and surface moisture the foam needs, and says “Clients should expect to vacate the work zone prior to application and not return until a period of time after application.”

Hold harmless agreement construction: does a liability policy cover it?

It turns on the policy and the clause. The commercial general liability form in Sonoma County’s published sample excludes liability assumed in a contract or agreement, but it carves out liability you would have without the contract, and liability assumed in an insured contract when the injury or damage occurs after it is signed. An insured contract includes the part of a business contract under which you assume another party’s tort liability for a third party’s bodily injury, or for damage to a third party’s property, with listed exceptions, such as a contract that indemnifies a railroad or an architect, engineer or surveyor for specified injury or damage. Your own policy’s version decides.

Indemnity clause construction contracts: can a state limit them?

Some do. Minnesota’s statute makes an indemnification agreement in a building and construction contract unenforceable except to the extent the injury or damage is attributable to the negligent or wrongful act or omission of the promisor or its independent contractors, agents, employees or delegatees, with an exception for an owner, responsible party or governmental entity that agrees to indemnify a contractor for strict liability under environmental laws. Ohio’s statute voids a promise in a contract for construction work to indemnify the promisee against liability for bodily injury to persons or property damage caused by the promisee’s negligence, where the promisee hired the promisor to perform the work, and it does not prohibit buying insurance from an Ohio-authorized insurer for one’s own protection or buying a construction bond.

Do I need a waiver of subrogation?

Whether you need one depends on the contract, so read it first. The sample workers’ compensation waiver reads “(This agreement applies only to the extent that you perform work under a written contract that requires you to obtain this agreement from us.)” Oregon’s Division of Financial Regulation says certificates “are issued for information only; they do not amend, extend, or change coverage.” The sample certificate the City of Sierra Madre publishes says “If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement.” Ask for the endorsement the contract names.

Insurance requirements for subcontractors: where do they come from?

A contract can set them. Oregon’s Division of Financial Regulation says “Construction contracts, leases, and arrangements for special events are all things that can require a certificate of insurance.” For subcontracts that require work on a Government installation, the FAR’s insurance clause says the prime contractor “shall require subcontractors to provide and maintain the insurance required in the Schedule or elsewhere in the contract.” Read the insurance section before you bid, and send it with your quote request.